Longwood Construction

Longwood Construction Photo

9/10/02 GRAINGER / UTILITY LINES UPDATE

Utility lines being excavatedThe reconstruction of Grainger is moving ahead very well and is on schedule! The installation of the steel framing will begin this week and you will see the building take shape very soon.

This week work begins to connect the electrical service as well as the air conditioning condenser water lines to Grainger. This requires some of the construction activity to move out from the Grainger site temporarily. Underground conduits will be installed from Grainger down Chambers St. behind Blackwell to connect to the transformer between Blackwell and South Ruffner that will provide the electricity for Grainger.

In addition to the electrical conduits condenser water lines for the air conditioning will be installed underground from the mechanical room in Blackwell (that serves Blackwell, Grainger and Ruffner) to the cooling tower located between Graham and the heating plant. The condenser water pipes will be in the same excavation as the electrical service behind Blackwell. At the corner of Blackwell they turn south, go down behind Hiner and Coyner to the entrance behind Graham, and across behind Graham to the cooling tower.

Beginning 9/10 the portion of Chambers St. behind Blackwell will be closed so this work may begin.  Access to the Tabb Circle area will remain open at all times through the Graham/Barlow parking lot. The Graham/Barlow parking lot will remain open throughout this utility construction period. A lane will also remain open to allow traffic to continue around Hiner to Pine St.

Once the work behind Blackwell is complete that area will be re-opened to traffic and parking. As the work moves down the street behind Hiner, some of the parking places behind Hiner will then be closed temporarily to allow for a traffic lane around the work area as it moves down the street. As the work passes the west entrance to the Graham/Barlow parking area, that parking lot will temporarily be accessible only through the Chambers St. entrance for several days. We know parking is already limited in this area and every effort will be made to minimize the number of parking places that are closed during this time. We will also try to complete this portion of work as quickly as possible so that the area can be returned to "normal."

The work in this area will continue for the next four to five weeks. As work progresses we will continue to post additional information regarding traffic changes, parking, and the progress of the work. Again we thank you for your patience during this period of intense construction. If you have specific questions, please do not hesitate to let us know.

 

Back to the latest

Facilities Management
Longwood University
Bristow Building, Farmville, VA 23909
Tel. 434.395.2089 | Fax. 434.395.2647
Email: construction@longwood.edu

Page updated: March 18, 2005
© 2005 Longwood University
Search / Site Index
Privacy Statement